mstrlucky74
Senior Member
- Location
- NJ
I always here conflicting answers to this. The thought is there is a time savings if you running parallel runs of conduits. Say if you have 5 sets of 3" conduits on a shared rack( say 200' point to point) should the labor unit be adjusted down for these conduits as opposed to running a single 3"? I usually adjust down 25% from the labor unit...so if I'm using 10 hours per C I would use 7.5 C for parallel runs.