I recently ran 2 secondary conduits for a service to a new building. I realized that ( after the building was almost done ) I was given 1200 Amp. switch gear . The two sets of 600 mcm would not do the job. I am now told to split up another set and pull two more conductors through each conduit. Derating aside is this legal to do? Yes or no where does it specify in the NEC?