PB Install

Should, unless they're trying to hang it working off of two ladders! If that's the case, and I was forced to, I would ask to be fired!:cry:
 
With the proper equipment on the job (such as a lift) it should be completed in far less than a day.
 
The answer is you have not provided enough information to answer the question.

I have seen it take a crew most of a day just to figure out how to get the lift to the vicinity of where the work is because of the maze of corridors and doors and equipment they have to pass thru to get there.

Or, think a second floor where the only access is via an old elevator that is too small for the lift.
 