Ewallace95
New User
- Location
- Sacramento CA
- Occupation
- Solar PM
Im trying to figure out if I can achieve the following task for a solar project (powerwall 3/backup switch). I have a split 400A Siemens panel and I am looking to move the 200A main breaker into the upper main breaker slot so I can run this feed to an isolated backup switch and then back to a sub feed kit on the circuit bussing in the MSP. I have to do this due to the fact that it is a 320A feed and the Tesla switch is only rated up to 200A. I was hoping to pull the feeders out of the main breaker and permanently terminate them (cap off) without voiding any UL listings and complying with NEC. My initial thought was to just use a Polaris to do this but I don't know if that's consider a permanent solution in this case. Please advise https://share.icloud.com/photos/066ImehonfORko31w6XDiTEkg