Permit pulled under an older code cycle

Status
Not open for further replies.

Minuteman

Senior Member
frisbeedog said:
I see the 30 amps for 10 in 2008. Other than special circumstances, how is that different than before? Copper?

Where is the #8 at 40 ocpd?

Not debating just curious, or tired, not sure which.

Not sure you specified the conditions of the circuits involved.
I don't remember just what the exact amps for the 3 A/C units are, but I checked them once recently, But the #10's are on a circuit with a min amps of 30 amps or less, and max amp and breaker of more than 30 amps. Same thing with the #8. The minimum is 40 or less the (I hope) and the max more. I will be by there in the morning and let you know.
 
cadpoint said:
Your a sub, What's Mr. Mdshunk Do ? This is it or I walk, Service and walk, Just walk....
I couldn't even tell who was on first, gezz did you just get paid ?
Gezz, what a night mare ...
Granted the fixes seems margin at best, still running on Construction power, I bet they could help you out, ID'n the Services
Cadpoint, were you working on energized equipment without your PPE? Or maybe a marathon CAD session?
 