tx2step
Senior Member
- Location
- North Texas, DFW area
Steve and Bob,
Thanks for the replies!
The ones that I will be installing will be on roof top package A/C units on top of a school. I don't want to make a lot of trips up to the roof for nuisance tripping.
SqD says the Time Mark #2664 and the SqD 8430 MPD are roughly equivalent. However the #2664 has an adjustable time delay in addition to having adjustable voltage settings.
It sounds like the Time Mark should work for the application.
Anyone else have any experience or opinion on this issue?
Thanks for the replies!
The ones that I will be installing will be on roof top package A/C units on top of a school. I don't want to make a lot of trips up to the roof for nuisance tripping.
SqD says the Time Mark #2664 and the SqD 8430 MPD are roughly equivalent. However the #2664 has an adjustable time delay in addition to having adjustable voltage settings.
It sounds like the Time Mark should work for the application.
Anyone else have any experience or opinion on this issue?