I was handed off a project that started before I got to the college and they just got an approval on the plan review that I am seeing for the first time. I am assuming that they can get away with running #10 from a 35A breaker because it is feeding motor circuits? I would like to feed these with cord drops from the ceiling that only like 15/20ft and want to make sure what I am think is ok. Can I use strain reliefs from a 4 square to a twist lock recept with a strain relief on it? would I need to add strain relief to the whip from the machine? Does my Recept have to be sized for the breaker or can I size it for the actual load like they did with the wire? if anyone has any suggestions on the best way to do it/products I'm all ears.