451F
Member
I was looking at a site last week and saw a 3 phase 200A MCB Load center with no breakers in it. It was fed from another building underground by color wrapped (size and metal not visible but MCB lug filling) conductors tapped off a 400 A disconnect. Two of the stabs were bolted to a pair of lugs to 3/0 CU which fed a sub panel load center without MCB (but full of breakers) in the same building.
I'm trying to determine if:
1. Is this existing installation going to pass inspection?
2. Can I add some breakers (25A load distributed over several) to the 200A MCB panel since it appears to be used as a disconnect now?
I do this work so seldom I have forgotten more than I knew.
I'm trying to determine if:
1. Is this existing installation going to pass inspection?
2. Can I add some breakers (25A load distributed over several) to the 200A MCB panel since it appears to be used as a disconnect now?
I do this work so seldom I have forgotten more than I knew.