I know this has been discussed before, and I have read through those posts. But the posts are quite old and I would like to bring it up again. We are working on a Hospital remodel and six floor addition. We are strongly considering using plug tail devices or something similar. Our thinking is that with only about 12 months to do this project, we are going to be quite compressed at the completion of this job. We feel that in order to prevent problems with per diem and high labor cost, bringing in out of town workers, we could use these on the rough in stage and use more economical labor at trim out. We are looking at about 6000 devices total and the cost difference equates to about a buck or two a device. And we haven't even beat up the suppliers yet. What I really would like to know is if anyone has any experience with these that could share their opinion and cautions in going this route. It seems like a good move at this point. But you never know until you are through.