The pool man is a friend. He gave the job to the town electrician. It's ok. He will be bonding I guess.
Here's the question. He will have 4 inch concrete poured. He will be using the 8 x 8 steal mesh in the pour.
The type you get in there and pull up during the pour.
The inspector wants the cu and mesh standing 1 inch off the ground before the pour
I'm not around the book but 3 inches down for the bond keeps entering my head
Is this what he's looking to see.
Should the inspector be concerned about the mesh or just the cooper or both?
Has anyone else had experience with this bond wire and a 4" deep pour.
Thank you
Here's the question. He will have 4 inch concrete poured. He will be using the 8 x 8 steal mesh in the pour.
The type you get in there and pull up during the pour.
The inspector wants the cu and mesh standing 1 inch off the ground before the pour
I'm not around the book but 3 inches down for the bond keeps entering my head
Is this what he's looking to see.
Should the inspector be concerned about the mesh or just the cooper or both?
Has anyone else had experience with this bond wire and a 4" deep pour.
Thank you