Long story short, I performed my own electrical work, and when I installed the junction box for the pool lights, I forgot about the spa height. Final inspection correction was to relocate it higher, which I did.
4 Pentair intellibrites with their own 1" conduit runs, and a 3/4" run to the transformers.
Looking to get a 2nd opinion on support ideas or if I'm good with what I have, before my final inspection.
https://photos.app.goo.gl/GhNUDZMAhyqnqX4h7
4 Pentair intellibrites with their own 1" conduit runs, and a 3/4" run to the transformers.
Looking to get a 2nd opinion on support ideas or if I'm good with what I have, before my final inspection.
https://photos.app.goo.gl/GhNUDZMAhyqnqX4h7