Is it typical in your installations where ground fault protection is required per 230.95, that the performance requirement found in 230.95(C) is done with primary injection testing or with some other less "all encompassing" method?
I believe that primary injection testing is the "only" real way, but I'm discussing the issue and am looking for other similar or dis-similar opinions.