I have a question on a project with a single-phase electrical service.
There’s a shed with a 60A 1 phase MLO panelboard at the corner of the property that’s fed from the main garage with a 1PH 100A panelboard, and the client is planning to install a 12kW PV grid tie system on the shed roof.
What's the correct way to tie the PV system into the existing setup?
Due to the bus size it can't backfeed the shed panel via breaker, would it be acceptable to tap PV disconnect directly to the shed feeder?
Or due to the main panelboard size will need to run a new separate conductors to the meter (which is several hundred feet away)?
Thanks!
There’s a shed with a 60A 1 phase MLO panelboard at the corner of the property that’s fed from the main garage with a 1PH 100A panelboard, and the client is planning to install a 12kW PV grid tie system on the shed roof.
What's the correct way to tie the PV system into the existing setup?
Due to the bus size it can't backfeed the shed panel via breaker, would it be acceptable to tap PV disconnect directly to the shed feeder?
Or due to the main panelboard size will need to run a new separate conductors to the meter (which is several hundred feet away)?
Thanks!