Epalmateer
Senior Member
- Location
- Michigan
- Occupation
- Electrician
House has two disconnects outside, 1 set of feeders from each disconnect goes down into crawl space and to 2 different panels. A portion of the feeders were damaged in the crawl, so I am replacing from the disconnect and about 15' into the crawl. I am going to install an enclosure in the crawl and use insulated lugs inside to make splices. Since there are splices, I technically have to connect all of the equipment grounds and bond the box, correct?