ThreeTenFifteen
Member
- Location
- Portland OR
- Occupation
- Electrician
Hello forum friends!
I'm looking at a mass timber project that consists of cross laminated timber with a 5" topping slab on each floor. I got into a discussion with a few co-workers about pulling wire in the ENT after rebar is dropped but before the concrete is poured. The reason for doing this would be to prevent having to coordinate wire pulling to light fixture outlets on the floor below, and also to ensure that there isn't any challenges with wire pulling after concrete is poured. Article 300.18(A) talks about runs needing to be complete before the installation of conductors. My thoughts are doing this is code compliant so long as the ENT is supported as required in 362.30 and terminated at both ends. I am curious if anyone has a different understanding on this? Or if there's anything to be mindful of if we decide to go this direction?
Thanks!
I'm looking at a mass timber project that consists of cross laminated timber with a 5" topping slab on each floor. I got into a discussion with a few co-workers about pulling wire in the ENT after rebar is dropped but before the concrete is poured. The reason for doing this would be to prevent having to coordinate wire pulling to light fixture outlets on the floor below, and also to ensure that there isn't any challenges with wire pulling after concrete is poured. Article 300.18(A) talks about runs needing to be complete before the installation of conductors. My thoughts are doing this is code compliant so long as the ENT is supported as required in 362.30 and terminated at both ends. I am curious if anyone has a different understanding on this? Or if there's anything to be mindful of if we decide to go this direction?
Thanks!