I am looking for clarification as to how many conductors I can get into a 2.5" sched. 80 PVC. I will be using #1 aluminum conductors, they will be direct buried and then run in PVC for protection when they emerge from the trench to the point they enter or leave the service panel. When looking at the notes in Chapter 9 motes to tables number 2 says " Table 1 applies only to complete conduit or tubing systems and is not intended to apply to sections of conduit or tubing used to protect exposed wiring from physical damage. So is that telling me I can use the total area or the 60%? I asume that I am still subject to derating factors found in article 310. Can anyone clear this up for me?