Hey there,
I have a proposed solar supply-side interconnection for a commercial building into an existing piece of switchboard. The roof-mounted PV inverters will land at a combiner box and main PV disconnect just outside the electric room at grade. From there, the PV will punch through the wall and enter the top of the main switchboard to land via a supply-side bus tap with cable limiters (behind the meter or ahead of the main). The gear is located in the center of the room. The AHJ (citing the adopted 2014 NEC) has insisted on the following: "Service entrance conductors are run inside the building from the main switchboard to PV disconnect ACD-1. Please demonstrate how the contractor will comply with Art. 230.6". I am not sure this would apply here, and if it did, then the majority of supply-side installations I have seen in my 13+ years would not be permitted. From 230.6, the implication would be that we need to bring our conductors in beneath the building foundation and up through the bottom of the gear, or provide a concrete or masonry chase to the gear. This seems like overkill and impractical at best. Would 230.6 really apply to the PV interconnection here? Are these considered service conductors or service entrance conductors? Are there other exceptions or permissions I can cite for this type of installation? Thanks in advance, and let me know if I can clarify anything.
I have a proposed solar supply-side interconnection for a commercial building into an existing piece of switchboard. The roof-mounted PV inverters will land at a combiner box and main PV disconnect just outside the electric room at grade. From there, the PV will punch through the wall and enter the top of the main switchboard to land via a supply-side bus tap with cable limiters (behind the meter or ahead of the main). The gear is located in the center of the room. The AHJ (citing the adopted 2014 NEC) has insisted on the following: "Service entrance conductors are run inside the building from the main switchboard to PV disconnect ACD-1. Please demonstrate how the contractor will comply with Art. 230.6". I am not sure this would apply here, and if it did, then the majority of supply-side installations I have seen in my 13+ years would not be permitted. From 230.6, the implication would be that we need to bring our conductors in beneath the building foundation and up through the bottom of the gear, or provide a concrete or masonry chase to the gear. This seems like overkill and impractical at best. Would 230.6 really apply to the PV interconnection here? Are these considered service conductors or service entrance conductors? Are there other exceptions or permissions I can cite for this type of installation? Thanks in advance, and let me know if I can clarify anything.