Need some help here:
1)In an operating rooms,should switches and outlets and any other devices operating over 10 volts be located above 5 feet?
2)If I understand it,The electrical system should be install as followed ,In rooms where flammable anesthetics are stored any switches, outlets,equipment disconnects need to be in explosion proof enclosure rigid pipe,conduit seals ect.. any duct work ,mechanical pipping or other system should not pass through these type rooms
Thank you for any input

Need some help here:
1)In an operating rooms,should switches and outlets and any other devices operating over 10 volts be located above 5 feet?
2)If I understand it,The electrical system should be install as followed ,In rooms where flammable anesthetics are stored any switches, outlets,equipment disconnects need to be in explosion proof enclosure rigid pipe,conduit seals ect.. any duct work ,mechanical pipping or other system should not pass through these type rooms