Depends on your operation, sometimes you never run into situation of it being possible to run everything at same time.Correct supposedly there is a load calculation I have not seen it. I know that it was a calculation of our power bills done over a year. The problem I have is that some of our machines here were not used during that time period.
What size transformer does POCO have. They might push it to some limits compared to what we will, but they generally are not going to supply you with something three times bigger than your highest peak demand, at least for anything over maybe 50 kVA.