bradbb2005
Member
- Location
- South Carolina
- Occupation
- Electrical Designer
We are moving into a new office building which we are designing the layout, systems, etc. The current configuration is parallel 2 1/4" conduits underground with 4-3/0 conductors stubbing up through the existing concrete floor feeding two separate 200A panels next to each other. The conductors are metered via CTs but are our responsibility from the pole. We are attempting to NOT run new conductors.
In my design, I was calling for the conduit to be cut back outside, routed to the side of the exterior, spliced and routed inside directly to the electrical room to the main panel (main disconnect), utilizing the parallel feeds for a 400AF/350AT Main panel.
We have had two electricians tell us this is not worth trying to do, one not giving a reason and one proposing to add a 90 to the stubbed conduit and re-route the conductors outside to a JBox, splice and run as designed. I have doubts about getting that approved and the architect won't be happy.
I am wanting to get a consensus from those in the field about a design that would facilitate a constructable product. I feel it should be more simple than what it is being made out to be. See attached images for clarity.
In my design, I was calling for the conduit to be cut back outside, routed to the side of the exterior, spliced and routed inside directly to the electrical room to the main panel (main disconnect), utilizing the parallel feeds for a 400AF/350AT Main panel.
We have had two electricians tell us this is not worth trying to do, one not giving a reason and one proposing to add a 90 to the stubbed conduit and re-route the conductors outside to a JBox, splice and run as designed. I have doubts about getting that approved and the architect won't be happy.
I am wanting to get a consensus from those in the field about a design that would facilitate a constructable product. I feel it should be more simple than what it is being made out to be. See attached images for clarity.