bonding jumper
Senior Member
I can't find any info about how to protect these devices in the NEC, My intuition says to treat them similar to a transformer, and I can protect the primary as long as the secondary is within 125 percent, but because rectifiers are not covered, I wonder if I might be required to do protection on both sides. Any ideas? Also, when sizing for a motor load, perhaps an elevator, should I size the rectifier to the FLA or the inrush? I was gonna go 125% of the fla, how does that sound? Thanks inadvance