A little slack is reasonable, but you can't leave feet of slack for every circuit.
Unless your employer is known for making last minute changes on a regular occurrence or you suspect the mounting area may be altered due to free space or another reason, I would say go for it and use the excess wires for jumpers
 
He's moving the panel 3 ft. Where in most circuits are you going to be able to have 3 ft of slack ????

 