I have read art. 344 yet I am still a little confused.
Here is the situation. I have a apartment complex that I am working with to straighten out some rough electrical on the property. One of the main things that we are working on is a trash compactor. The existing feed is ran direct buried and has shorted out. it goes under 60 ft of freshly repaved asphalt, 2 side walks and flower beds. I am thinking about using heavy duty cable protector ramps and running RMC through it. what code would I be in violation of?
Here is the situation. I have a apartment complex that I am working with to straighten out some rough electrical on the property. One of the main things that we are working on is a trash compactor. The existing feed is ran direct buried and has shorted out. it goes under 60 ft of freshly repaved asphalt, 2 side walks and flower beds. I am thinking about using heavy duty cable protector ramps and running RMC through it. what code would I be in violation of?