What are y'all building that requires 500 sets of 2/0 4C SER to be sent through a fire wall?
Modular apartments; presumably 500 separate fire walls:
Size the junction box for SER Cable Splicing
This is a multifamily building project with modular apt units. Each apt unit is delivered to the site from the factory as a module. It has a 4#2/0 & 1#1G AL SER Cable whip. We need to make connections between the SER cable from the modular unit to the 4#2/0 & 1#1G AL MC Cable from the building...