Hey Everyone,
I have a project where I need to splice a heat trace into a circuit at some exposed downspouts every 25' along the side of a 800' long warehouse. I'm looking for a way to run 3/4" EMT without doing box offsets to save headaches while pulling cable.
Essentially from the control cabinet I'll go 25', JB, another 25', JB ect. every 6 drops I need to start a new circuit. I have limited space to run conduit so I can't do a bunch of dedicated runs out to each drop. See below

I have no problem putting box offsets in but the bend counts get wild when I think about actually pulling cable. I Would like to keep the conduit straight for ease but the options I'm coming up with aren't great:
1) Cut some 5/8" unistrut into small pieces, strap it to the building and strap the pipe to it
2) Run 1" EMT instead of 3/4" so the offsets are minimal and the conduit is roomy
3) strap the pipe with mineralac straps (mini's) direct to the building face to stand them off the building for straight box entry
4) Run the 3/4" with normal offsets and install a larger JB every 6-7 drops as a pull point and splice everything through at each of these locations.
Frankly I don't really like any of them, I'm thinking option three is easiest from a labor perspective but I've never used those straps like that, not even sure if its code compliant in NY where this is going.
Any thoughts?
I have a project where I need to splice a heat trace into a circuit at some exposed downspouts every 25' along the side of a 800' long warehouse. I'm looking for a way to run 3/4" EMT without doing box offsets to save headaches while pulling cable.
Essentially from the control cabinet I'll go 25', JB, another 25', JB ect. every 6 drops I need to start a new circuit. I have limited space to run conduit so I can't do a bunch of dedicated runs out to each drop. See below

I have no problem putting box offsets in but the bend counts get wild when I think about actually pulling cable. I Would like to keep the conduit straight for ease but the options I'm coming up with aren't great:
1) Cut some 5/8" unistrut into small pieces, strap it to the building and strap the pipe to it
2) Run 1" EMT instead of 3/4" so the offsets are minimal and the conduit is roomy
3) strap the pipe with mineralac straps (mini's) direct to the building face to stand them off the building for straight box entry
4) Run the 3/4" with normal offsets and install a larger JB every 6-7 drops as a pull point and splice everything through at each of these locations.
Frankly I don't really like any of them, I'm thinking option three is easiest from a labor perspective but I've never used those straps like that, not even sure if its code compliant in NY where this is going.
Any thoughts?