Is you had choice to install( in duct banks) schedule 40 or 80 pvc which would you choose? Thinking pretty much same from labor standpoint.
Yes but why? TYSchedule 40 if underground.
Larger ID and lower material cost, and schedule 80 adds no value to the installationYes but why? TY
Unless it affects the required burial depth, e.g. under a road or driveway.I agree with Don if it's being buried Sch80 is overkill and a waste of money.
Shouldnt burial depth should be the same for either Sch 40 or 80?Unless it affects the required burial depth, e.g. under a road or driveway.
Engineer might specify it.
Concrete encased or direct bury?Is you had choice to install( in duct banks) schedule 40 or 80 pvc which would you choose? Thinking pretty much same from labor standpoint.