I have a job coming up where the 3/4" Sch 40 PVC is underground. Where it emerges above grade I will be moving over to Sch 80 for about 12". My dilemma, the conduit fill is fine for the Sch 40 but for the Sch 80 is "over filled" by .0092
Do I need to rethink the conduit size needed for the entire run or let it "ride"?