Have schedule with building description shown below. My work is all inside. I have no underground temp etc. but I do have lightning protection so there is some underground counterpoise I could do early. My question is based on the descriptions when would you say temp stringers could be installed? I'd say after superstructure complete.
How about interior feeder work and rough in? I'd assume shortly after "Start Enclosure"?

Point is I'm not really sure based on "superstructure" and "start enclosure" descriptions what that exactly means and what stage of the building that would be.

Superstructure would be steel going up etc. I believe. Start enclosure would be just that....starting to make building weathertight? Curtain walls etc.? Thanks.