- Location
- Lockport, IL
- Occupation
- Semi-Retired Electrical Engineer
This question came to me from a field office. In the main switchboard and in the first panel downstream of a separately derived system, we will have separate ground and neutral bars, with main/system bonding jumpers connecting the two bars. But I can't find a code reference that forbids simply using one bar for both the green and the white wires. Is there such a requirement? 250.28(B) seems to imply that you can have just one bar, as long as there is a properly identified screw bonding the bar to the panel enclosure.