Hi friends,
I just have a quick question.
I know based on NEC we need to bound all the ground together or in other word we cannot have a separate ground and all the ground wires need to be connected.
But I have a special case on which I would like to get your opinion.
I have a plant. Inside a plant there is a building which is far from the rest of the plant (around 200'). This building has a separate service point. Am I allowed to used a separate ground for that building because the service point is different from the plant service point?
I just have a quick question.
I know based on NEC we need to bound all the ground together or in other word we cannot have a separate ground and all the ground wires need to be connected.
But I have a special case on which I would like to get your opinion.
I have a plant. Inside a plant there is a building which is far from the rest of the plant (around 200'). This building has a separate service point. Am I allowed to used a separate ground for that building because the service point is different from the plant service point?