shaneo
Member
- Location
- Oceanside, ca., USA
Ok, so I have a good friend who has installed a 125A MLO rated subpanel (cutler hammer) fed from a Siemens 200A load center MLO which is fuse protected at the MSB (also Siemens). My question is this...in a typical situation like this (for siries rating) the 125A rated subpanel should have a main breaker installed instead of a MLO rated at the 200A breaker that is feeding the 200A MLO load center but since the 200A MLO is protected from fuses would he still have to install a Main Breaker in the 125A subpanel? Whew, that was a lot sorry. Am I assuming this correctly? I'm not really sure why he didn't just install the same manufacture brand...thanks in advance