Existing historical building repair & service upgrade (it is an old house but used as museum now):
Existing main disconnect/panelboard is in the basement.
1. Service disconnect (MCB in the panelboard below) - "inside nearest the point of entrance" - Is about 2 feet from the wall close enough?
2. Working space for a new panelboard - in the basement the bottom of the floor joists above is about 6 feet. There is no place on the upper floors where the panelbd can be installed.
Existing main disconnect/panelboard is in the basement.
1. Service disconnect (MCB in the panelboard below) - "inside nearest the point of entrance" - Is about 2 feet from the wall close enough?
2. Working space for a new panelboard - in the basement the bottom of the floor joists above is about 6 feet. There is no place on the upper floors where the panelbd can be installed.