Service is 480/277/3ph/4W/60Hz
We have the following loads:
Three 50HP/3ph motors.
10kw/3ph Unit Heater
15KVA/3ph Transformer (480-208Y/120)
If only 2 motors will ever run at any time.
Do all three motor FLA's have to be used in determining the utility service size?
Do electrical interlocks, that prevent the third pump from running, have any effect on the size of the utility service?
We have the following loads:
Three 50HP/3ph motors.
10kw/3ph Unit Heater
15KVA/3ph Transformer (480-208Y/120)
If only 2 motors will ever run at any time.
Do all three motor FLA's have to be used in determining the utility service size?
Do electrical interlocks, that prevent the third pump from running, have any effect on the size of the utility service?