Installed an service entrance rated ATS next to a main breaker panel. Installed 2 - 2" conduits between panel and ATS, ran un-spliced service entrance conductors through one conduit to ATS main breaker, then load side conductors back through second conduit to main breaker. Grounds and neutrals separated accordingly. Inspector is not allowing the service entrance conductors to be run though the panel to the ATS but won't provide code article that it violates. A little help please?