There is a requirement to have a grounding electrode system at the shed if you have more than one branch circuit though.Is there a code for minimum circuit that you need to run to a shed for power. The shed is already pre wired.
Sent from my iPhone using Tapatalk
I think you are only allowed one branch circuit or feeder to a detached structure. Unless it's a mwbc, I believe.There is a requirement to have a grounding electrode system at the shed if you have more than one branch circuit though.
A MWBC is considered a single circuit.I think you are only allowed one branch circuit or feeder to a detached structure. Unless it's a mwbc, I believe.
There is a requirement to have a grounding electrode system at the shed if you have more than one branch circuit though.
250.32.What article is that?