raludovico
Member
- Location
- US
Why can't my single phase 20 kW generator provide power for a three-phase panel box with a load of 10 kW. All of the load circuits are 120 volt in the three-phase box. I understand that 1 phase will not work. This will be OK because of critical circuits only will be energized in the 3 phase panel box. There is no locked rotor amperage to be considerate. The loads have been calculated and measured over a 30 day period. Could somebody please show me in the NEC for any violation. Thank you
Sent from my VS810PP using Tapatalk
Sent from my VS810PP using Tapatalk

don't have to be 20kw cause of the shared loads just gotta sync em