horrorsix
Member
- Location
- Harrisburg PA
I'm looking to install a 400A 120/208v 3 phase sub panel in a commercial facility. 480V primary, I have two questions. The electrical room is 245' from the sub panel location. Should the transformer be at the electrical room or closer to the sub panel? My second question is obviously wire and transformer size. I was looking at installing a 112.5Kva.
Existing equipment to be hooked up is
2 machines rated at 78A 3 phase each= 156A
2 machines rated at 70A 3 phase each= 140A
total of 296A
400A panel gives some room for expansion. Does this not look right to anyone?
Thanks
Shawn
	
		
			
		
		
	
				
			Existing equipment to be hooked up is
2 machines rated at 78A 3 phase each= 156A
2 machines rated at 70A 3 phase each= 140A
total of 296A
400A panel gives some room for expansion. Does this not look right to anyone?
Thanks
Shawn
			
				Last edited: 
			
		
	
								
								
									
	
		
			
		
		
	
	
	
		
			
		
		
	
								
							
							 
				
 
 
		