SLAB..BEAM OR NOT

Status
Not open for further replies.

Alwayslearningelec

Senior Member
Location
NJ
Occupation
Estimator
So if you wanted to rack a few 3/4" or 1" conduits you would have to determine wither a beam clamp is required or an anchor and to do that you would reference either structural or arch drawings? Correct? Thanks,.
 

tkb

Senior Member
Location
MA
Then you would have to drill and set an anchor.

When estimating, I usually carry a beam clamp.
The cost covers an anchor or beam clamp.
The labor to install an anchor is a little more but it is offset by the cost of a beam clamp.

Also it would depend on the specific job conditions and the specifications of what materials get used.

I would also look on the structural drawings.
 
Last edited:

Alwayslearningelec

Senior Member
Location
NJ
Occupation
Estimator
Then you would have to drill and set an anchor.

When estimating, I usually carry a beam clamp.
The cost covers an anchor or beam clamp.
The labor to install an anchor is a little more but it is offset by the cost of a beam clamp.

Also it would depend on the specific job conditions and the specifications of what materials get used.

I would also look on the structural drawings.

Thanks. But what about the labor for drilling. That's covered when using a beam clamp? Seems like you might be a little short.
 

tkb

Senior Member
Location
MA
Thanks. But what about the labor for drilling. That's covered when using a beam clamp? Seems like you might be a little short.

If it a few anchors it shouldn't be much of a problem.
If it a major run, you need to be sure of the specific conditions.
 