What would be the best way/procedure to set these sleeves in poured concrete slab? They are going in a telecom closet? Thank you!:D
 

Attachments

  • Capture 2.jpg
    Capture 2.jpg
    13.1 KB · Views: 1
  • Capture.jpg
    Capture.jpg
    12 KB · Views: 1

infinity

Moderator
Staff member
Location
New Jersey
Occupation
Journeyman Electrician
What would be the best way/procedure to set these sleeves in poured concrete slab? They are going in a telecom closet? Thank you!:D

If it's metal deck then are you drilling a hole in the metal for each sleeve?

The space between them needs to be at least 3x the size of the largest aggregate. Did the architects allow for that?

Typically these areas of the deck are designed to accommodate what is shown in the detail.
 

mstrlucky74

Senior Member
Location
NJ
If it's metal deck then are you drilling a hole in the metal for each sleeve?



Typically these areas of the deck are designed to accommodate what is shown in the detail.
so your asking about cutting metal deck? also how is the area or that slot accommodated for? thanks

Sent from my SM-N960U using Tapatalk
 

infinity

Moderator
Staff member
Location
New Jersey
Occupation
Journeyman Electrician
so your asking about cutting metal deck? also how is the area or that slot accommodated for? thanks

Yes, if there's a metal deck are you drilling a hole in the metal to allow the sleeve to penetrate to the ceiling below or are they leaving a big open slot to accommodate the sleeves?
 

gadfly56

Senior Member
Location
New Jersey
Occupation
Professional Engineer, Fire & Life Safety
Yes, if there's a metal deck are you drilling a hole in the metal to allow the sleeve to penetrate to the ceiling below or are they leaving a big open slot to accommodate the sleeves?

This is the best way to do it. No muss, no fuss, and you just pack it all with fire sealant after the sleeves are set.
 