Sometimes we have to seperate out labor and materials because there is sales tax on materials and not on labor. I believe this is for a new construction project only, but I am not sure of this. You are supposed to show your marked up materials and the sales tax applied. This is always on private work and not public.
 

Chamuit

Grumpy Old Man
Location
Texas
Occupation
Electrician
I usually get a sinking feeling when asked that. A lot of times the customer wants to see how much labor is going to cost. then you have to give alittle lecture on how paying a guy $10 an hour costs more then just $10 an hour. They never get it.

On another note. Here the tax is payed on the whole project. The tax is N% on parts and labor combined because it's contracting not Sales & Service. If you had a store front and were selling items retail wise it'd be different.
 