Derek4325
Member
- Location
- Caroga Lake NY
- Occupation
- Electrician
The obvious answer is install at the top. However I dont know what to do here. I have a 200A homeline meter main 20 space that is going to feed through to a 200A subpanel inside the house. Sub feed wires will go through the bottom of the meter /Main via conduit. The feed through breaker has the lugs angled to where you would want to install on the right side of the panel. I also plan on installing a generator breaker with an interlock kit that requires the top 2 spaces on the right side. To complicate things further i will be installing a surge protector breaker that also needs to be placed as close to the main as possible. What do you guys suggest? Thanks in advance.