electrical contractor will be pulling 4 600 kcmil conductors in ridgid conduit up to the 6th floor of a bulding.there will be 4 runs of pipe. should the wires that are inside pipe be supported so the weight of all the wires dont put a strain on terminals when thay are landed and cause problems , or even fall back down the pipe. i have heard of this happening . is there such a device called a wedge which you place inside the pipe to help prevent this? is there other means which could redemy this problem ? is it also mandated in any part of the code i cant seem to find any reference . any help would be appreciated .