Strapping flex conduit

Status
Not open for further replies.

signguy1

Member
I am presently being told by an electrician on a jobsite that my flexible conduit must be strapped 12" from termination point. I have always used 24"
from termination, every 48" after. I need to know who is correct. Also if the conduit penetrates a wall is the penetration considered an adequate substitute for a strap. Any help would be greatly appreciated.
 

infinity

Moderator
Staff member
Location
New Jersey
Occupation
Journeyman Electrician
I would note that there are a number of exceptions that allow FMC to be unsupported or supported at varying intervals at it's termination.
 