Mvillines
Senior Member
- Location
- Western KY on the Ohio River
This is an installation installed on a dwelling last week. This is a transfer switch with the service conductors entering the top of the panel and the generator conductors are entering the right side near the bottom. There are four conductors leaving the bottom of the panel serving the MDP. All conductors are of the correct size and type.
The item I believe to be in violation is taken from part II of article 250. Maybe other violations I missed. Oh yes?.the printed circuit board is not secured, waiting for the clips to arrive.
The item I believe to be in violation is taken from part II of article 250. Maybe other violations I missed. Oh yes?.the printed circuit board is not secured, waiting for the clips to arrive.