I have a project I inspected that has the main disconnect located on the side of a building 60 feet from new building. A 4-wire was run from disconnect into panel in basement of new structure. Contractor bonded grounded conductor and grounding electrode conductor at "sub-panel" in new building. He is stating that since the new panel has a main breaker, that is the way it needs to be completed instead of isolating neutrals and grounds. Sadly, we are still under the 2008 NEC. What is the best way to explain to him that they not to be separated after the main disconnect switch, regardless of whether it is in a separate building.