Woodway
New member
- Location
- California
Question from another forum and now it's got me interested. One of the posters has a home under construction with temp power pole in yard. The service at the pole is tied to combination panel (panel with meter and breakers). He didn't say but I assume that the pole is bonded to ground rod. The panel has 200 amp disconnect with "feed through lugs" at the bottom of each buss bar. The guy get OK from local inspector on pole install and 100 amp single phase feed from pole combo panel to an on site trailer. Then he runs a three wire cable (two phase wires and neutral) from the "feed through lugs" to the main panel in the house by using a trench between the two. The panel in the house is bonded to a second ground rod system and has it's own disconnect . He gets two answers from two inspectors on the cable in the trench. One inspector ok's the three wire cable while a second inspector says that before he can give the OK he, the building owner, must first install a four wire cable in the trench and not tie the neutral and equipment grounds together at the house panel. What is correct here? Article 250-32(b)(2) was my choice as the controlling article for this setup. Was I correct there was no continuous metallic path between the grounding system at the pole and at the house (ie. No equipment ground was installed in the trench between the house and the pole, only the neutral wire was installed with the two hots) Note, at the house the neutral from the three wire cable was bonded to the panel and ground rod system of the house and the house panel has it's own disconnecting means.
I'm always open to new ideas and correcting those that I have wrong . Great forum for learning and expanding electrical code background.
I'm always open to new ideas and correcting those that I have wrong . Great forum for learning and expanding electrical code background.