Re: Tele/data wiring in Electric Room
If he wanted additional money, then he should have gotten approval before doing the work. He cannot justify the added costs on the basis of an NEC requirement, nor on the basis of what he thinks the Inspector would "want." There may be a local code of which I am not aware, but I doubt it. The decision to pay, or not pay, the added costs may well come down to working relationships (i.e., do you want to keep working with this person/company?).