Have a very large site. Need to temp out a few buildings that are being relocated then demolished. Services currently run underground. The services are between 200A and 600A depending on the building.
Since they will require temp feeders I'm trying to decide whether they would be run overhead or underground. I'm worried if overhead makes most sense they could be in way of construction machines, truck etc.
Thought?
Since they will require temp feeders I'm trying to decide whether they would be run overhead or underground. I'm worried if overhead makes most sense they could be in way of construction machines, truck etc.