New construction temporary lighting is not an issue for me. What I'm looking for is ideas/suggestions on how you do this. Once rough framing is up and they want to start drywall they always want some lights working. Here's how I do it...when roughing in I try to hit each room or rooms/halls first switch then put in a temp outlet there and jump switch leg to that outlet. Usually that give me enough light and then off and on with breaker. Any other ideas?