Good morning everyone,  I need some help for folks much smarter than myself.
I am working on planning a project at an industrial facility and was asked to evaluate their temp. power needs. They have set 10 blast resistant buildings they will need power supplied to. What I have a available is (2) temp power racks, each one has a 75 kva transformer and a distribution panel with a 225A main.
Any thoughts on if this is sufficient?
Thank you
	
		
			
		
		
	
				
			I am working on planning a project at an industrial facility and was asked to evaluate their temp. power needs. They have set 10 blast resistant buildings they will need power supplied to. What I have a available is (2) temp power racks, each one has a 75 kva transformer and a distribution panel with a 225A main.